Frenchtown to Walla Walla section next for U.S. Highway 12 four-laning project - This Washington Department of Transportation illustration shows the planned route for Phase Six of the U.S. Highway 12 four-laning project.
This Washington Department of Transportation illustration shows the planned route for Phase Six of the U.S. Highway 12 four-laning project.
Construction to begin in spring 2008,
completion scheduled for October 2009
 Construction Phases  The Washington State Department of Transportation says construction on U.S. Highway 12 four-laning will continue next spring on Phase Six. The approximately eight-mile project will four-lane the highway from McDonald Road near Lowden to its intersection with Pine Street in Walla Walla.
   The advertisement for bids is expected during this winter (2008), with construction scheduled to begin in the spring. The new four-lane section is scheduled for completion by October 2009.
   According to the WSDOT’s most recent quarterly report, the project is “on schedule, on budget and on scope per the approved 2007-2009 transportation budget.”
   Funding for the $66.4-million improvement is being provided by a combination of state and federal gas tax revenues.

US12 logoThe U.S. Highway 12 Coalition, an alliance of public and private organizations, has successfully lobbied Congress and the Washington State legislature for funding for U.S. Highway 12 four-laning. To learn more about the Coalition’s efforts visit its Web site at www.ushighway12.com